Home
  Background
  Careers
  Clients
  Contact Us
  Decentralized WW

NITROGEN TREATMENT
PHOSPHORUS TREATMENT
NON POINT RUNOFF
STORMWATER/
GROUNDWATER TRTMNT
  Malibu, CA
  List of Publications
  Portfolio
  Publications Available for Download
  Search
  Services
  Testimonials
  Cluster Wastewater Systems Planning Handbook
  PHOSPHORUS GEOCHEMISTRY in Septic Tanks, Soil Absorption Systems, and Groundwater
  Springfield, PA Act 537 Wastewater Plan Update
  FTP Access
Comprehensive Decentralized Wastewater Management Facility Plan
for Canaan Valley, West Virginia

Project Objective

This project is to prepare a comprehensive Decentralized Wastewater Management Facility Plan for Canaan Valley, in Tucker County West Virginia, in collaboration with the Canaan Valley Institute (CVI). The goal is sustainable wastewater management systems in the Valley that are protective of water quality and public health.

This project builds upon the work performed for the Wastewater Management Feasibility study. The Executive Summary provides a brief summary of the study. If you would like the full report, please contact Lombardo Associates, Inc. at 617-964-2924 or Canaan Valley Institute at 800-922-3601.

To view a PowerPoint presentation summarizing the Feasibility Study process click here.

Project Description

To view the Project Decentralized Wastewater Management Facilty Plan Introduction Click Here

The project will consist of the following activities.

  1. Comprehensive Decentralized Wastewater Management Facility Plan

    The plan will include the following to the extent available information allows:
    • Data Collection
    • Existing Needs for WWTFs
    • Existing Wastewater Needs for Unsewered Areas
    • Future Wastewater Needs --based on 20 year projections
    • Wastewater Needs Summary
      To view the Wastewater Needs Summary Click Here
    • Identification of Technically Viable Scenarios
      To view the Identification of Technically Viable Scenarios Report Click Here
    • Management Alternatives Evaluation
      To view the Management Alternatives Evaluation Report Click Here

    To view a Powerpoint presentation detailing the facility planning process
    click here.

    To view the PowerPoint presentation summarizing the wastewater needs assessment and preliminary cost estimates from the January 11th public meeting click here.

  2. Public Participation

    In collaboration with CVI, public input will be solicited to define the most probable solutions. Engineering expertise will interact with local concerns to describe potential project outcomes. Public participation is a key element of the Canaan Valley wastewater management planning process.

    This web site will be an important tool to help disseminate information about the project. As reports are generated, they will be posted here. Additionally project & public meetings will be held to actively involve the public and stakeholders.

    Public Meetings
    Click here for the minutes from the July 28, 2005 kickoff meeting
    Click here for the minutes from the December 13, 2005 public meeting
    Click here for the minutes from the December 13, 2005 WWTF Owners Meeting
    Click here for the minutes from the January 11, 2006 public meeting
    Click here for the minutes form the February 15, 2006 public meeting.

    Project Meetings
    Click here for the November 10, 2005 meeting minutes
    Click here for the December 13, 2005 meeting minutes
    Click here for the January 11, 2006 meeting minutes

    Additionally project newsletters were prepared to help communicate information about the project with the public.

    Click here for the November 2005 newsletter.
    Click here for the February 2006 newsletter.

  3. Comparative Summary of Chosen management Option

    A detailed comparative summary of the chosen decentralized management option and updated centralized sewer plan will be provided

    To view the Comparison of Centralized and Decentralized Wastewater Management Stratergies Report Click Here

  4. Project Summaries and Approval Documents

    • Preferred Plan Summaries for engineering of the proposed project, cost of the proposed project (capital costs, O&M, retirement of existing debt), project funding plan, projected user rates, project schedule, land and easements required, and public health benefits.
      To view the Preferred Plan Report Click Here
    • Brief Environmental Assessments of proposed project
Project Schedule

July 28, 2005 Project kick-off meeting
November 10, 2005 Project meeting
December 13, 2005 Project meeting, WWTF owners meeting, and public meeting
January 11, 2006 Project meeting and pubic meeting
February 15, 2006 Project meeting and pubic meeting
February 26, 2006 Project completion